Fibre Reinforced Facade Encyclopedia: Installation

A facade installer is the contractor who receives panels, substructure components and fixings and converts them into a weathertight, structurally adequate external wall on the building. The role is routinely underestimated in specifications, which describe the panel in detail and the installation in a paragraph. In practice the installer controls setting out, tolerance absorption, fixing torque and embedment, flashing continuity, sealing and the sequence in which the wall is closed, which between them decide whether the facade performs as designed.

A tested, certified panel installed on the wrong bracket, at the wrong torque, over a torn weather barrier, is a non-compliant wall made of compliant parts.

At a glance

PropertyTypical valueNote
Typical procurementSupply and install, or supply only plus separate installSupply and install concentrates responsibility
Core scopeSurvey, setting out, substructure, panel fixing, flashingsPlus sealing, protection and making good
Australian licensingState based building trade licensingRequirements differ by state and work value
Height workHigh risk construction work under WHS regulationsSafe work method statement required
Competence evidenceComparable projects and system specific trainingManufacturer training certificate
InsurancesPublic liability, and professional indemnity where design is transferredPI matters if the installer sizes fixings
Inspection hold pointsBarrier, substructure, first panel, each levelWritten into the specification
Records requiredMarked-up panel map, fixing and torque recordsPart of the handover documentation
Warranty interfacePanel, system and workmanship warranties are separateGaps between them are where claims fail

What the scope actually covers

  • Survey of the completed structure and comparison against the design model, before fabrication is released
  • Setting out from agreed datums and grid lines, establishing panel line, plumb and level references
  • Receipt, unloading, inspection and site storage of panels, with damage recorded on arrival
  • Installation of brackets and substructure, fixed into the structure to the tested embedment and edge distances
  • Packing and shimming to absorb structural deviation within the adjustment range of the system
  • Fixing of panels to the specified fastener, torque and sequence, following the panel map
  • Flashings, cavity closures, cavity barriers and baffles in the correct sequence relative to the panels
  • Sealing of joints where the system is sealed, including priming and backing rod
  • Protection of the installed facade until handover, and cleaning down at completion
  • As-built records: panel placement, fixing and torque records, photographs and non-conformance reports

Licensing and registration in Australia

There is no single national facade installer licence. Building trade licensing is administered by the states and territories, and the applicable requirement depends on the state, the class of building, the value of the work and the trade classification. A specifier should require the installer to hold the licences applicable in the jurisdiction of the project and to provide evidence, rather than nominating a licence class that may not exist in that state.

What has changed since the combustible cladding failures is the level of scrutiny attached to external wall work. Registration requirements for building practitioners, statutory declarations on materials and evidence of conformance for external wall products are now routine on projects covered by the National Construction Code non-combustibility provisions (check the edition adopted in your jurisdiction). Installers are increasingly expected to demonstrate documented competence with the specific system rather than general cladding experience. Work at height is separately high risk construction work under the work health and safety regulations, with programme and cost consequences that belong in the tender documents.

How the package is procured

Two models dominate, and the choice affects risk more than price. In a supply and install package, the panel manufacturer or a facade contractor takes responsibility for panels, substructure, fixings and installation as one scope, so a defect cannot be argued between the maker and the fixer and the fixing system is the one the panel was designed around. The field of tenderers is narrower and the price includes the risk premium for site work.

In a supply only package, panels are procured from the manufacturer and installed by a separate subcontractor, often the trade already doing other cladding. It can be cheaper, but the interface is the risk: the manufacturer warrants the panel, the installer warrants the workmanship, and any defect that could be either falls into the gap. Where this model is used, require the installer to be trained and approved by the panel manufacturer for that system, and require the manufacturer to attend site for the first panels and at defined hold points.

Either way the fixing system is not a free variable. A panel is designed, tested and warranted with a particular anchor and bracket arrangement, and substituting a cheaper fixing changes its structural behaviour and undermines the basis of the design. If the package allows fixing substitution, it should require written approval from the panel manufacturer and a re-check by the facade engineer.

What to ask for, and what to inspect

The competence evidence worth requiring is specific and verifiable: two or three comparable completed projects with the same or a closely similar system, with contacts; evidence of training or approval by the manufacturer of that system; the licences applicable in the project jurisdiction; insurances at the required levels; the nominated site supervisor and their experience; and a sample of quality records from a previous project, which tells you more than the rest.

The inspection regime should be written into the specification as hold points rather than left to discretion. As a minimum: the weather barrier inspected and photographed by elevation before the substructure covers it; the substructure inspected for fixing type, embedment, edge distance and alignment before panels go on; the first panel of each type installed and inspected before the run proceeds; a defined proportion of fixings checked for torque with records; flashings and cavity closures inspected before they are concealed; and a final inspection with the panel map marked up as built.

Standards and references

  • NCC 2022 Volume One, external wall provisions and Specification 7 (check the edition adopted in your jurisdiction)
  • State and territory building practitioner registration and trade licensing requirements for the project jurisdiction
  • Work Health and Safety Regulations, high risk construction work and work at height
  • AS/NZS 4284 Testing of building facades, where project or system testing applies
  • AS 5216 Design of post-installed and cast-in fastenings in concrete, for fixings into the structure
  • AS 1170.0 and AS/NZS 1170.2 for the actions the installed system must resist
  • GRCA and panel manufacturer installation manuals for the specific system, including fixing type, torque and tolerance

Related terms

Questions specifiers ask

Is there a national facade installer licence in Australia?

No. Building trade licensing is administered by the states and territories, and what applies depends on the jurisdiction, the class of building and the value of the work. Require the installer to hold the licences applicable to the project’s jurisdiction and to provide evidence.

What does an installer’s scope include beyond fixing panels?

Survey of the structure, setting out from datums, receipt and storage of panels, substructure and bracket installation, packing and shimming, panel fixing to the specified torque and sequence, flashings and cavity closures, sealing, protection until handover, and the as-built records.

Is supply and install better than supply only?

It concentrates responsibility, so a defect cannot be argued between the maker and the fixer, and the fixing system is the one the panel was designed around. Supply only can be cheaper but creates an interface risk; if it is used, require the installer to be trained and approved by the panel manufacturer for that system.

Can the installer change the fixings?

Not without written approval. A panel is designed, tested and warranted with a particular anchor and bracket arrangement, and a substitution changes its structural behaviour and undermines the basis of the design. Any change should be approved by the manufacturer and re-checked by the facade engineer.

Which inspections should be hold points?

The weather barrier before it is covered, the substructure before panels go on, the first panel of each type before the run proceeds, a proportion of fixings checked for torque, and flashings and cavity closures before they are concealed. Concealed work cannot be inspected later.

Procuring a moulded panel facade as supply and install, or as supply only with a separate installer? We can work either way and will say which suits the job. Talk to us about delivery